A cookie is information stored on your computer by a website you visit. Cookies often store your settings for a website, such as your preferred language or location. This allows the site to present you with information customized to fit your needs. As per the GDPR law, companies need to get your explicit approval to collect your data. Some of these cookies are ‘strictly necessary’ to provide the basic functions of the website and can not be turned off, while others if present, have the option of being turned off. Learn more about our Privacy and Cookie policies. These can be managed also from our cookie policy page.
IE10 and below are not supported.
Contact us for any help on browser support
The Oxley PDA Development Scheme was approved by the Queensland Government and came into effect on 9 August 2019.
Download Oxley PDA Development Scheme
The proposed development scheme was publicly notified from 25 February to 5 April 2019. A submissions report assessing the submissions and any amendments to the proposed development scheme was prepared.
Download Oxley PDA Submissions Report
The development scheme is the regulatory document that assists with planning, carrying out, promoting, coordinating and controlling land development within the PDA.
The Oxley Priority Development Area (PDA) was declared on 10 August 2018 and an interim land use plan (ILUP) given effect. The development scheme supersedes the Interim Land Use Plan that has been in place since declaration of the PDA.
The Oxley PDA Development Scheme was approved by the Queensland Government and came into effect on 9 August 2019.
Download Oxley PDA Development Scheme
The proposed development scheme was publicly notified from 25 February to 5 April 2019. A submissions report assessing the submissions and any amendments to the proposed development scheme was prepared.
Download Oxley PDA Submissions Report
The development scheme is the regulatory document that assists with planning, carrying out, promoting, coordinating and controlling land development within the PDA.
The Oxley Priority Development Area (PDA) was declared on 10 August 2018 and an interim land use plan (ILUP) given effect. The development scheme supersedes the Interim Land Use Plan that has been in place since declaration of the PDA.
Please find attached the latest information about importing fill to the site here.
For more information about site access and an added Q&A about Stage 1 and 2 vegetation removal, please see the Document Library.
Please see the latest project update here.
The latest Q&As about the Stage 1 - DA approval are located here.
Please see the latest construction update here.
Please view here for the Oxley PDA construction update July 2020.
For Oxley PDA FAQ's please visit here
For more information please visit here
The development application (DA) for approval of the Oxley Priority Development Area (PDA) Masterplan and Stage 1 development, was lodged in February 2020.
A range of reports and documents were prepared for, and submitted with, the development application including but not limited to landscape plans, traffic impact assessment, civil engineering report, stormwater management plan, geotechnical report, ecology assessment, bushfire management plan and vegetation clearing and fauna management plan.
The application and supporting documents can be viewed online by searching DEV2020/1099.
A public notification period is to run for a 21 business day period from 8 April to 11 May 2020, giving the community a formal process to have their say on the proposal.
Submissions can be made via post or email. Further details on how to make a submission, can be found online.
Oxley secondary college closed and was declared surplus to government needs in 2001.
Community newsletter 1 was distributed to 9500 local households and businesses about community engagement opportunities.
An online survey was available for residents and the community to complete.
Two 'talk to a planner' information sessions were undertaken, plus a facilitated community-led engagement process.
EDQ established a Community Panel to facilitate community knowledge session.
The Community Panel held two knowledge sessions for the local community.
Community Panel presented their draft findings from the knowledge sessions to EDQ.
A cluster of 8 small sink holes were identified on the site. Detailed geotechnical investigations commenced and initial rectification works completed. Monitoring and treatment of sink holes and critical landslip remains ongoing.
Community newsletter 2 outlining the results of the engagement activities undertaken to date was distributed.
EDQ met with interested and community organisations regarding inclusion in the development plans.
The Queensland Government launched the Advancing our cities and regions strategy, which will see surplus and underutilised state property renewed and repurposed. Under this strategy Oxley is identified as a South-East Queensland urban renewal precinct.
EDQ
Queensland Government caretaker period, election and post election departmental changes.
EDQ continued site investigations with a view to informing future redevelopment options, site protection and ensuring all information is current in relation to the site.
EDQ held two community information sessions seeking the community's view on a concept and design principles.
Oxley declared a Priority Development Area (PDA) and Interim Land Use Plan (ILUP) adopted.
Demolition of existing school buildings.
Public notification of development scheme.
All submissions will be reviewed and the final development scheme prepared.
Development scheme approved.
Contractor was appointed
Site possession and establishment
Vegetation clearing undertaken
Remediation works commence